east electric company - Kazanluk Ltd.
East Elektric Company - Kazanluk (eec-K) is an eec's subsidiary. We are preparing two construction sites for construction of wind farms. Both are on our own land in surrounding of the city of Kazanluk just in the foothills of Mountain "Stara Planina", bordering on Enel's wind-farm site (250,000 sq.m).
The wind conditions of both areas have been explored for a long time (click the rouses on the left). The measurements are going on. After obtaning the monthly average values** of the wind velocity for the last ten years, EEC-K proceeded with purchase the land syndicated from plenty of plot owners. Next, eec-K will apply for exchange the purpose of the land form agricultural use as it is now into industrial land for development of renweables. Then the market price of the land will rise up to about four times.
Further it is following the process of of obtaining the licenses and other certificates as the Bulgarian regulations so require for wind farm construction, the purchase/selling contract of the wind power generated including. In the meantime the business is subject of negotiation for sale to prospective investor—in part or in whole (land, project, certificates, and the whole acquisitions of eec-K).
Kazanluk-1, Ultrasound Measurement at 10 m and software extrapolation to 80 m height
Month |
1 |
2 |
3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | AVERAGE | |
Average Velocity |
9.0 | 8.8 | 6.5 | 7.1 | 7.3 | 7.7 | 6.6 | 6.0 | 6.0 | 5.0 | 5.6 | 6.7 | 6.86 | Expected annual average: |
Destination |
N |
NE | EE | SE | S | SW | W | WN | TOTAL |
Percent hours with velocity of >= 6 m/sec, 72% |
||||
Percent Cases | 20 | 12 | 6 | 7 | 3 | 10 | 12 | 30 | 100 |
Number of hours with wind velocity >=6 m/s, 6,576 |
Kazanluk-2, Ultrasound Measurement at 10 m and software extrapolation to 80 m height
Month |
1 |
2 |
3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | AVERAGE | |
Average Velocity |
7.7 | 9.0 | 7.1 | 8.0 | 6.5 | 6.5 | 5.8 | 6.0 | 7.1 | 7.7 | 7.7 | 7.9 | 7.25 | Expected annual average : |
Destination |
N |
NE | EE | SE | S | SW | W | WN | TOTAL |
Percent hours with velocity of >= 6 m/sec, 100% |
||||
Percent Cases | 20 | 12 | 6 | 7 | 3 | 10 | 12 | 30 | 100 |
Number of hours with wind velocity >=6 m/s, 8,760 |
_______________
* The exact number and the generators' output power depend on both the construction design and supplier of the equipment for each site.
** The data have been taken from satellite watch made by one of the leading world services for several levels over the world level; we apply
the information for level 10 m only.